Type: New build 54 bedroom hotel with Function Room, Gym Health Spa and Salon

Working direct to the client, Town & Country have been involved since engineering stages in January 2019.

The 3 story hotel spans 2000m2 and boasts 54 executive rooms, a function room, gym, salon and a health spa all set within its own extensive grounds.

All of the below have been fully installed and project managed by Town & Country from design to completion

  1. Full site survey and ground investigation report
  2. Reduce level excavation and removal of all excavated material off site
  3. Engineer set out all foundations and structural pad foundations
  4. Excavate and pour concrete to all foundations and structural pads
  5. Precision cast 80 bolt boxes within the structural pads ready to receive steel
  6. Form elevator shaft with tanking and waterproofing to suit
  7. Install all foul and surface water drainage
  8. Install 2000m2 reinforced concrete floor
  9. Install attenuation tank
  10. Installation of all utility services
  11. Formation of roadways and service road construction with a new 200 vehicle car parking facility into site.
  12. Tarmac surfacing to all roadways and car parking areas
  13. Retaining walling and Kerbing to site
  14. Paving and finishes

Get in touch to discuss how

Town and Country

can enhance your project

Call us on 01782 416 279

Get in touch to discuss how

Town and Country

can enhance your project

Call us on 01782 416 279